A Class 5 estimate answers one question: is this project in the right order of magnitude for the budget? It is the number for a feasibility study, a screening meeting or a first budget authorization, built from the little that is known at concept stage.
The nine trades
Sitework and utilities; structure (concrete, masonry, steel); envelope (roofing, cladding, windows); interior finishes (drywall, flooring, paint, doors); mechanical; plumbing; electrical; fire protection; and general conditions with overhead and profit. Each is adjusted on its own for building type, quality, storeys and location, so the split is as useful as the total.
Reading the range
For buildings, AACE International Recommended Practice 56R-08 puts Class 5 accuracy at -20 to -30 % on the low side and +30 to +50 % on the high side. The low and high figures here are the trade ranges added up; the midpoint is a reasonable planning number. As the design develops, Class 3 and then Class 1 estimates by a professional estimator replace it.
Canadian projects
The indices are US-based and the figures are in US dollars. The trade structure is the same on a Canadian job, so pick a state with a similar market, convert, and treat the result as the starting point for a proper takeoff.